West Midlands GDV Calculator and BCIS Build Cost

West Midlands build cost 1,467 to 1,937 £/sqm (BCIS estate housing quartiles rebased to Rugby, December 2025). GDV 270 to 460 £/sqft. Birmingham, Coventry, Worcester. Birmingham CIL bites on city schemes.

BCIS build cost per sqm

  • Estate housing, lower quartile: 1,467 £/sqm
  • Estate housing, median: 1,728 £/sqm
  • Estate housing, upper quartile: 1,937 £/sqm
  • Flats, median: 1,997 £/sqm (quartiles 1,649 to 2,433)

BCIS figures rebased to Rugby, as reprinted in Local Plan Viability Study (BNP Paribas Real Estate for Rugby Borough Council, December 2025, Appendix 5). BCIS data last updated 29 Nov 2025, rebased to Rugby (location index 100). 5-year sample. BCIS rates are gross internal floor area, include preliminaries and exclude external works, fees, contingency and VAT. BCIS itself is subscription-only; this is the most recent public reprint we found for the region.

GDV working band

Resale GDV 270 to 460 £/sqft (low to high). Mid 340 £/sqft. Sense-check against current Land Registry Price Paid postcode-area aggregates before committing a bid.

Birmingham CIL bites on city schemes; HMO yield path strong in Coventry.

Birmingham CIL

  • Birmingham CIL is significant on city schemes. Always model it as a per-sqm line, not a percentage of GDV.
  • Coventry HMO yield path stays strong on student stock.

HMO yields in West Midlands

  • Coventry, Wolverhampton and Birmingham university suburbs trade student HMOs on 8 to 10 percent gross yields.
  • Capitalised GDV proxies hold where Land Registry comparables are thin.

Open the workbench with these rates

Inputs
MAX LAND BID£187,899At 20% profit on cost, 9 units, 950 sqft GIA each.
MARGINAL
GDV£2,470,950
Build cost£1,372,586
Prof fees£164,710
s106/CIL/BNG£108,000
Contingency£123,397
Finance interest£126,019
Target profit£378,943
Total costs (excl land)£1,894,713
Senior debt @ LTGDV£1,606,118
PoC18.6%
PoGDV15.7%
LTC77.1%
Sensitivity (PoC %)
Build -5%Build +5%Build +10%Build +15%Build +20%
GDV -15%16%6%1%-3%-7%
GDV -10%20%12%7%3%-1%
GDV -5%19%18%13%9%4%
GDV 0%18%19%19%14%10%
GDV +5%17%19%19%20%15%

Cells show profit-on-cost percentage at each GDV stress / build-cost shock pair. Cells below your target PoC turn amber-warm; cells below 10 percent abort.